Maryland Bridge Replacement to Cost $1.7-$1.9B; Progressive Design-Build to Be Used

Maryland officials told the media yesterday that the replacement cost for the Francis Scott Key Bridge in Baltimore is now between $1.7 and $1.9 billion, and that the state hopes to have a replacement structure in place by 2028 by using the “progressive design-build” engineering technique.

Maryland Transportation Secretary Paul Wiedefeld also told the Baltimore Sun that the $350 million payout from the Chubb Group for the state’s insurance policy on the bridge will be transferred to the Federal Highway Administration’s Emergency Relief program for reimbursement of bridge replacement costs (assuming that FHWA does indeed wind up funding the replacement bridge out of the ER program – it is likely, but not guaranteed yet).

Replacing this bridge will be much more expensive than the last two high-profile Interstate highway bridges replaced with federal ER funding. The Interstate 35W bridge in Minneapolis that collapsed in 2007 was replaced at a cost of $234 million, and the Interstate 10 Twin Spans outside New Orleans, damaged by Hurricane Katrina in 2005, cost $803 million to replace.

The Maryland Transportation Authority (MDTA – the MDOT toll facility subgroup that actually owned and operated the FSKB) is hoping to move quickly to select a design-build firm for the bridge project. MDTA is holding an all-comers “Key Bridge Rebuild Virtual Industry Forum” on Tuesday, May 7 from 2-4 p.m. to brief potential consultant firms, contractors, and subcontractors, all of whom should bookmark MDTA’s webpage http://www.keybridgerebuild.com for more information.

What is “progressive design-build”? Well, regular design-build is hiring one firm to perform or manage both the design and construction elements of a project (pretty straightforward). However, in regular design-build, the contractor is hired after the concept and preliminary design of a project are complete – the industry standard is the 35 percent mark of total completeness of design. Then the design-build contractor comes in and finishes the other 65 percent of the design and actually builds the thing.

Progressive design-build would actually hire a design-build firm at the absolute beginning, before the conceptualization or any other design work has been done. (Obviously, this means that the contractor cannot be selected by the usual kind of cash bidding.) The contractor works with the client to develop the project together. A primer from the Design-Build Institute of America sets out the process:

A key feature of progressive design-build is protection of the purchaser through setting a Guaranteed Maximum Price (GMP), putting responsibility for cost overruns above that price on the contractor, not the purchaser. That GMP can either be set before design (“Design to Fixed GMP Value” on the above flowchart), or at the end of final design (“Design Fixed Scope, Then Set GMP Value”), which is more likely in this instance.

Maryland was a leader in using progressive design-build, having used the technique in 2017 on the I-270 Innovative Congestion Management project.

Search Eno Transportation Weekly

Latest Issues

Happening on the Hill

Related Articles

Senate Assesses Aftermath of Francis Scott Key Bridge Collapse

Jul 12, 2024 | Steven Parks
July 12, 2024 - On March 26, the Francis Scott Key Bridge, which spanned the Patapsco River in Baltimore, Maryland,...

House Subcommittee Convenes Roundtable to Discuss Fleeting U.S. Maritime Competitiveness

Jul 12, 2024 | Kirbie Ferrell
July 9, 2024 - The House Subcommittee on Coast Guard and Maritime Transportation hosted a roundtable to hear from industry...

Senate Committee Discusses Trade and Customs Policy

May 24, 2024 | Kirbie Ferrell
May 21, 2024 - The Senate Subcommittee on International Trade, Customs, and Global Competitiveness held a hearing on Tuesday titled...

Maryland Bridge Replacement to Cost $1.7-$1.9B; Progressive Design-Build to Be Used

May 3, 2024 | Jeff Davis
May 2, 2024 - Maryland officials told the media yesterday that the replacement cost for the Francis Scott Key Bridge...

Biden Announces Plan to Assist U.S. Steel, Shipbuilding Industries

Apr 19, 2024 | Jeff Davis
April 19, 2024 - President Biden this week requested higher tariffs on Chinese-made steel and aluminum, and his trade rep...

Balancing Act: The Next Generation of Mariners in the Maritime Industry

Mar 28, 2024 | Rear Admiral Ann C. Phillips, U.S. Navy (Ret.)
March 28, 2024 - Throughout my years of service as a Naval Officer I was frequently reminded that experience matters....

Senate Begins WRDA Deliberations

Mar 1, 2024 | Garett Shrode
March 1, 2024 - The Senate Committee on Environment and Public Works held a hearing to discuss the projects, programs...

House Panel Looks at Impacts of Red Sea Shipping Disruptions

Feb 2, 2024 | Kirbie Ferrell
February 2, 2024 - A House subcommittee this week looked at the impacts of Houthi missile launches on maritime shipping...

Year-End Defense Bill Contains Maritime Reauthorization

Dec 8, 2023 | Jeff Davis
December 8, 2023 - Next week, the Senate will vote on a 2,305-page, $874 billion national defense authorization bill early...

House Subcommittee Meets to Discuss Autonomous Maritime Technology, Submarines

Sep 22, 2023 | Kirbie Ferrell
September 19, 2023 - The House Subcommittee on Coast Guard and Maritime Transportation met to discuss the use of autonomous...

The History of the Inland Waterways Trust Fund

Aug 31, 2023 | Jeff Davis
August 31, 2023 - The story of the creation of, and changes to, the Inland Waterways Trust Fund

As Other Agencies Face Cutbacks, House Appropriators Give Corps Water Program 15% Increase

Jun 16, 2023 | Jeff Davis
June 16, 2023 - A draft bill approved in an House subcommittee yesterday would provide $9.6 billion in new funding...